Timeline & Progress
-
Tucker playground survey created for community feedback. Take the survey here.
-
We’re excited to share that we have officially signed a contract with Kyle Zick Landscape Architects (KZLA), an award-winning firm known for designing safe, creative, and inclusive play spaces. Learn more at https://www.kylezick.com/about.
-
Interviews with landscape architect firms in progress
Milton’s community preservation committee recommended grant request for $102,000 to cover Landscape Architectural and Engineering Services- pending Town Meeting approval in May 2026
Sen. Driscoll, Rep Wells and Rep Fluker-Reid agreed to earmark $100,000 in FY27 budget for Tucker’s playground
-
Milton’s Community Preservation Committee grant submitted to cover $102,000 in design and engineering costs.
-
Tucker mural project unveiled — thank you to Lee Beard and our student artists! This was grant funded by NEFA, Mass cultural counsel and Milton cultural counsel
Site survey completed by Morse Engineering and funded by PTO
Community Updates
Project Timeline
Phase 1 – Planning (2024–2025) completed
Playground Committee formed (parents, school, and MPS leadership)
Public mural project launched and installed in partnership with artist Lee Beard, students and staff
Site survey completed (funded by the PTO)
Phase 2 – Design & Construction Preparation (2025–2026) in progress
Design firm selection
Community design input
Schematic design and design development
Finalize construction documents
Phase 3 – Construction (2026–2027)
Remove old equipment and install new playground structures
Add athletic field, outdoor classroom, and landscaping
Completion Target- Fall 2027